Status of research plan as per project proposal

Research activity

Comment

Status

Infiltration experiment – Cape Town

Set up pilot experiment – Yr 1

Ongoing

Ongoing testing – Yr 2, Yr 3

Not yet started

Evaluation – Yr 3

Not yet started

WSD inventory and evaluation – Johannesburg

Inventory of WSD initiatives – Yr 1, Yr 2

Ongoing

WSD feasibility at mixed-use development – Yr 2

Ongoing

Development of guidelines for implementation of stormwater by-law – Yr 3

Not yet started

Systems / actor analyses

Evaluating GI regimes and niches – Yr 1

Ongoing

Identification / enrolment of stakeholders for transition arenas (10 participants in each city)

Multi-actor network for arena workshops – Yr 1

Ongoing

Workshop no. 1 – Cape Town

Project start-up, masterclass in WSUD – June 2019

Completed

Workshop no. 1 – Johannesburg

Project start-up, masterclass in WSUD – June 2019

Completed

Transition arena workshop no. 2 – site visits to pilot (Cape Town)

Stakeholder engagement – Yr 2

Not yet started

Transition arena workshop no. 2 – test sites (Johannesburg)

Stakeholder engagement – Yr 2

Not yet started

Transition arena workshop no. 3 – Cape Town

Dissemination, discussion of results; water sensitive future vision-building – Yr 3

Not yet started

Transition arena workshop no. 3 – Johannesburg

Dissemination, discussion of results; water sensitive future vision-building – Yr 3

Not yet started

Water sensitive futures symposium – Cape Town

Yr 3

Not yet started

Water sensitive futures symposium – Johannesburg

Yr 3

Not yet started

Annual internal project meetings / workshops

Yr 1 – Cape Town (aligned with transition arena 1)

Completed

Yr 2 – mid-term meeting in Copenhagen

Not yet started

Yr 3 – Cape Town (aligned with transition arena 3)

Not yet started

Advisory board meetings

Yr 1 – Gauteng (aligned with transition arena 1)

Completed

Yr 3 – Cape Town (aligned with transition arena 3)

Not yet started

IWA World Water Congress 2020, Copenhagen

Yr 2

Not yet started

Workshop in the framework of the network ‘Vand i Byer’

Yr 3

Not yet started